      North American Planned, Unplanned Refinery Shutdowns (Table)
      2008-06-20 07:35 (New York)

      By Robert Tuttle
          June 20, 2008 (Bloomberg) — Following is a table of scheduled and unplanned
      refinery shutdowns, maintenance, new plants and capacity expansions in North
      America. The list only includes work that could be confirmed.
      To search for refinery outages, enter {REFO <GO>}.
          Shutdown Type: P: Planned, U: Unplanned, N: Non-maintenance

      Refinery                                     Refinery                          
      Owner                  Shutdown              Capacity                          
      Location                 Type    Period        b/d     Notes                   

      ——————————————————————————–
      New Information:Delek LaGloria             N     Jun 18, 08    58,000  CDU, alkylation shut by 
      Delek
      US Holdings Inc              to                  power failure. Units    
      Texas, U.S.                      Jun 19, 08            restarted.              

      Delek LaGloria             N     Jun 10, 08    58,000  Power failure shuts     
      Delek US Holdings Inc              to                  unspecified units.      
      Texas, U.S.                      Jun 11, 08            Operations restarted.   
                                                            Production loss not     
                                                            specified.              

      Current Outages:
      Exxon Mobil Torrance       P     Jun 13, 08   155,000  Sulfur recovery unit    
      Exxon Mobil Corp                   to                  shuts for maintenance.  
      California, U.S.                 Jun, 08                                       

      Motiva Norco               P     May 30, 08   220,000  Hydrocracker shuts for  
      Saudi Arabian Oil Co,              to                  mainteance late May for a
      Royal Dutch Shell PLC            Jun 30, 08            month.                  
      Louisiana, U.S.                                                                

      Alon Big Spring            N     Feb 18, 08    70,000  Full shutdown by an     
      Alon Israel Oil Co                 to                  explosion in the        
      Ltd                              Jul 15, 08            propylene unit. Fires   
      Texas, U.S.                                            erupted in asphalt and  
                                                            slop oil tanks. The     
                                                            refinery processing     
                                                            35,000 bbl/day as of    
                                                            April 7. FCCU expected to
                                                            resume service by the end
                                                            of July.                

      Husky Lima                 P     Jan, 08      160,000  No major outage planned 
      Valero Energy Corp                 to                  for 2008.               
      Ohio, U.S.                       Dec 31, 08                                    

      Southland Lumberton        N     Dec 01, 06     5,800  confirmed with EIA that 
      Southland Oil Co                   to                  the refinery is out of  
      Mississippi, U.S.                N/A                   service since Dec 01 2006

      Parkland Bowden            N     Jan 01, 01     6,500  Parkland owns a refinery
      Parkland Income Fund               to                  at Bowden, Alberta which
      Alberta, Canada                  N/A                   suspended production in 
                                                            2001. Parkland has been providing processing    
                                                            services to a local petrochemical plant to  
                                                            produce fluids used in the oilfield on a       
                                                            customer fee basis. These services offset some of 
                                                            the ongoing costs of maintaining the site. We
                                                            have been able to take advantage of the tanks at
                                                            the refinery for interim fuel storage to help    
                                                            balance our supply contract volumes and have
                                                            refurbished the tanks and system to ensure this is
                                                            a viable revenue producer longer term.

      Future Outages:Petro-Canada Edmonton      P     Qtr 3, 08    135,000  Full shutdown of 135,000
      Petro-Canada                       to                  bbl/day refinery during 
      Alberta, Canada                  Qtr 4, 08             the second half 2008 to 
                                                            allow new units to be   
                                                            added to the plant as   
                                                            part of an upgrade.     

      Conoco Wood River          P     Qtr 3, 08    306,000  Catalytic cracker       
      EnCana Corp,                       to                  maintenance to install  
      ConocoPhillips                   Qtr 4, 08             wet-gas scrubbers to    
      Illinois, U.S.                                         reduce emissions.       

      Frontier El Dorado         P     Aug, 08      112,000  New coker to start      
      Frontier Oil Corp                          to                  operations in August,   
      Kansas, U.S.                              Aug, 08          capacity 3,000 barrels a day.                    

      Holly Woods Cross          P     Aug, 08       26,000  Turnaround planned.     
      Holly Corp                         to                                          
      Utah, U.S.                       Sep, 08                                       

      Sunoco Toledo              P     Qtr 3, 08    150,000  CDU, FCC units to shut in
      Sunoco Inc                         to                  third quarter           
      Ohio, U.S.                       Qtr 3, 08             maintenance.            

      Holly Woods Cross          P     Qtr 4, 08     26,000  Hydrocracker, capacity  
      Holly Corp                         to                  15,000 barrels a day,   
      Utah, U.S.                       Qtr 4, 08             planned to start production. Crude       
                                                            refining capacity to rise to 31,000 barrels a day.

      Navajo Artesia             P     Jan, 09       75,000  New hydrocracker,       
      Holly Corp                         to                capacity 15,000 barrels a
      New Mexico, U.S.                 Jan, 09       day, expected to start production. Turnaround   
                                                             planned.                

      Valero Krotz Springs       P     Qtr 1, 09     83,000  Full turnaround planned 
      Valero Energy Corp                 to                  for 2009.               
      Louisiana, U.S.                  Qtr 4, 09                                     

      Giant Yorktown             P     Qtr 3, 09     61,900  Turnaround scheduled for
      Giant Industries Inc               to                  late 2009, no more      
      Virginia, U.S.                   Qtr 4, 09             specific details available.              

      Marathon Garyville         P     Qtr 4, 09    275,000  New CDU, VDU,           
      Marathon Oil Corp,                 to              hydrocracker (capacity  
      Ashland Inc                      Qtr 4, 09         70,000 b/d), delayed    
      Louisiana, U.S.                                     coker (44,000 b/d), 
      reformer (65,000 b/d),  
                                                            kerosene hydrotreater (47,000) planned to come
                                                            on line, raising refinery throughput to 425,000   
                                                            barrels a day.          

      Motiva Port Arthur         P     Qtr 1, 10    285,000  New units to add 325,000
      Motiva Enterprises                 to                  b/d crude capacity, to  
      LLC                              Qtr 4, 10             start in 2010.          
      Texas, U.S.                                                                    

      Valero Port Arthur         P     Qtr 4, 10    325,000  New Hydrocracker        
      Valero Energy Corp                 to              construction to be      
      Texas, U.S.                      Qtr 4, 10         completed, capacity 50,000 barrels a day, to
                                                              start in 4Q 2010.       

      Sinclair Tulsa             P     Qtr 4, 10     60,000  New CDU, hydrocracker,  
      Sinclair Oil Corp                  to                  coker units planned to  
      Oklahoma, U.S.                   Qtr 4, 10        start operations.Capacity to increase to 
                                                                               115,000 barrels a day. 
       

      Total Port Arthur          P     Qtr 1, 11    240,000  New Coker (50,000 b/d), 
      Total SA                           to                  desulfurization and     
      Texas, U.S.                      Qtr 4, 11        vacuum distillation unit.The $2.2 billion project
                                                            is scheduled to be completed in 2011
      .      

      Valero Port Arthur         P     Qtr 2, 11    325,000  New Coker construction to
      Valero Energy Corp                 to               be completed, capacity  
      Texas, U.S.                      Qtr 2, 11         45,000 barrels a day, during 2Q of 2011.      
                                                                              Refinery throughput to  rise to 415,000 b/d
      in  
                                                               conjunction with related investments.            

      Consumers’ Co-op           P     Jan, 12       50,000  New CDU expansion to add
      Regina                             to                  30,000 b/d capacity, also
      Federated                        Dec, 12           add FCC complex, planned
      Co-operative Ltd                                    to start operations in 2012.
      Saskatchewan, Canada                                                    

      Historical Outages:
      Shell Deer Park            U     Jun 18, 08   340,000  FCC wet gas compressor  
      Royal Dutch Shell                  to                  trips.                  
      PLC, Petroleos                   Jun 19, 08                                    
      Mexicanos                                                                      
      Texas, U.S.                                                                    

      Delek LaGloria             N     Jun 18, 08    58,000  CDU, alkylation shut by 
      Delek US Holdings Inc              to                  power failure. Units    
      Texas, U.S.                      Jun 19, 08            restarted.              

      Pasadena                   P     Jun 11, 08   106,500  FCC unit upset. No      
      Nationale A                        to                  additional details      
      Portefeuille                     Jun, 08               available.              
      Texas, U.S.                                                                    

      Shell Deer Park            N     Jun 10, 08   340,000  FCC shuts in brief outage
      Royal Dutch Shell                  to                  after compressor fails
      PLC, Petroleos                   Jun 11, 08                                    
      Mexicanos                                                                      
      Texas, U.S.                                                                    

      LyondellBasell             N     Jun 10, 08   287,000  CDU shut during storm.  
      Houston                            to                  Restart confirmed.      
      Lyondell Chemical Co             Jun 11, 08                                    
      Texas, U.S.                                                                    

      Delek LaGloria             N     Jun 10, 08    58,000  Power failure shuts     
      Delek US Holdings Inc              to                  unspecified units.      
      Texas, U.S.                      Jun 11, 08            Operations restarted.   
                                                            Production loss not     
                                                            specified.              

      Valero Port Arthur         P     Jun 08, 08   325,000  distillate hydrotreater 
      Valero Energy Corp                 to                  shuts for maintenance.  
      Texas, U.S.                      Jun 12, 08                                    

      Valero Wilmington          U     Jun 06, 08   135,000  FCC, alkylation shut by 
      Valero Energy Corp                 to                  leak. Restart confirmed.
      California, U.S.                 Jun 09, 08                                    

      Conoco Borger              P     Jun 06, 08   146,000  FCC shut for repairs.   
      ConocoPhillips,                    to                                          
      EnCana Corp                      Jun 09, 08                                    
      Texas, U.S.                                                                    

      ConocoPhillips             U     Jun 03, 08   247,000  FCC shuts for repairs.  
      Alliance                           to                  Restart confirmed.      
      ConocoPhillips                   Jun 18, 08                                    
      Louisiana, U.S.                                                                

      Valero Delaware City       U     Jun 03, 08   190,200  Coker rates cut because 
      Valero Energy Corp                 to                  of boiler fault. Restart
      Delaware, U.S.                   Jun 06, 08            confirmed.              

      Motiva Port Arthur         N     Jun 02, 08   285,000  Full shutdown after power
      Motiva Enterprises                 to                  cut. Restart began June 
      LLC                              Jun 05, 08            5.                      
      Texas, U.S.                                                                    

      BP Texas City              P     May 31, 08   470,000  Hydrocracker            
      BP PLC                             to                  (ultracracker) shuts.   
      Texas, U.S.                      Jun 05, 08            Additional details not  
                                                            available.              

      Big West Oil               U     May 30, 08    68,000  Sulfur recovery unit    
      Bakersfield                        to                  shuts.                  
      Flying J Oil & Gas               May 30, 08                                    
      Inc                                                                            
      California, U.S.                                                               

      BP Carson                  P     May 29, 08   265,500  Coker shuts for         
      BP PLC                             to                  maintenance.            
      California, U.S.                 Jun, 08                                       

      Flint Hills Corpus         N     May 27, 08   300,000  FCC, sulfur recovery    
      Christi                            to                  units shut after loss of
      Koch Industries Inc              Jun, 08               steam.                  
      Texas, U.S.                                                                    

      Valero Paulsboro           U     May 26, 08   195,000  FCC shuts because of a  
      Valero Energy Corp                 to                  leak. Restart confirmed.
      New Jersey, U.S.                 Jun 01, 08                                    

      Conoco Sweeny              P     May 19, 08   216,000  Hydrotreater for        
      Petroleos de                       to                  distillates shuts for   
      Venezuela SA,                    May 31, 08            catalyst change.        
      ConocoPhillips                                                                 
      Texas, U.S.                                                                    

      Chevron El Segundo         P     May 16, 08   260,000  CDU, 70,000 b/d capacity
      Chevron Corp                       to                  shuts for `several weeks’
      California, U.S.                 Jun, 08               of maintenance.         

      Sunoco Philadelphia        U     May 16, 08   330,000  CDU, gulfiner units shut.
      Sunoco Inc                         to                  Restarts confirmed June 
      Pennsylvania, U.S.               Jun 04, 08            4.                      

      Valero Three Rivers        P     May 16, 08    95,000  FCC shuts for 10 days of
      Valero Energy Corp                 to                  maintenance.            
      Texas, U.S.                      May 26, 08                                    

      Countrymark Mount          P     May, 08       23,500  Vacuum tower starts     
      Vernon                             to                  production mid-May,     
      Countrymark                      May, 08               raising capacity by 3,000
      Cooperative Inc                                        b/d. Fuel output to rise
      Indiana, U.S.                                          by 45 million gallons a 
                                                            year, mostly diesel.    

      Valero Wilmington          P     May 11, 08   135,000  Partial shutdown after  
      Valero Energy Corp                 to                  power failure.          
      California, U.S.                 May 18, 08                                    

      Delek LaGloria             U     May 11, 08    58,000  FCC rates cut by boiler 
      Delek US Holdings Inc              to                  failure. Restart        
      Texas, U.S.                      May 16, 08            confirmed.              

      Shell Martinez             U     May 09, 08   165,000  Hydrocracker shuts for a
      Royal Dutch Shell PLC              to                  week.                   
      California, U.S.                 May 16, 08                                    

      Shell Canada Sarnia        U     May 08, 08    71,820  Runs cut as unit outage 
      Royal Dutch Shell PLC              to                  curbed gasoline         
      Ontario, Canada                  May 17, 08            production. More specific
                                                            details not available.  

      Hovensa St. Croix          N     May 08, 08   495,000  CDU shut for unscheduled
      Petroleos de                       to                  repairs.                
      Venezuela SA, Hess               May 16, 08                                    
      Corp                                                                           
      US Virgin Islands,                                                             
      U.S.                                                                           

      Navajo Artesia             U     May 07, 08    75,000  FCC shut after          
      Holly Corp                         to                  malfunction. Restart    
      New Mexico, U.S.                 May 24, 08            confirmed.              

      Flint Hills Corpus         P     May 05, 08   300,000  Sulfur recovery unit No.
      Christi                            to                  2 shuts for maintenance.
      Koch Industries Inc              May 15, 08                                    
      Texas, U.S.                                                                    

      Valero Corpus Christi      P     May 02, 08    38,000  CDU, Vaccum units shut  
      West                               to                  for two weeks as of May 
      Valero Energy Corp               May 16, 08            2. Restart confirmed.   
      Texas, U.S.                                                                    

      Holly Woods Cross          N     May 01, 08    26,000  Alkylation unit shut    
      Holly Corp                         to                  after fire. Restart     
      Utah, U.S.                       May 08, 08            confirmed.              

      Total Port Arthur          P     Apr 30, 08   240,000  Sulfur recovery unit and
      Total SA                           to                  units 804, 823, 824 and 
      Texas, U.S.                      May, 08               825 shut.               

      BP Carson                  U     Apr 28, 08   265,500  Hydrodesulfurization unit
      BP PLC                             to                  breakdown. Restart      
      California, U.S.                 May 01, 08            confirmed.              

      BP Texas City              P     Apr 25, 08   470,000  FCC No. 1, alkylation,  
      BP PLC                             to                  coker units shut.       
      Texas, U.S.                      May 28, 08                                    

      Imperial Oil Sarnia        U     Apr 25, 08   121,000  Runs cut by boiler      
      Exxon Mobil Corp                   to                  failure and repair.     
      Ontario, Canada                  May, 08                                       

      Murphy Superior            P     Apr 23, 08    35,000  Full shutdown to last   
      Murphy Oil Corp                    to                  about a month.          
      Wisconsin, U.S.                  May 25, 08                                    

      Total Port Arthur          U     Apr 21, 08   240,000  Hydrotreater rates cut  
      Total SA                           to                  because of malfunction
      Texas, U.S.                      Apr, 08                                       

      Alon Big Spring            N     Apr 19, 08    70,000  Sulfur recovery unit No.
      Alon Israel Oil Co                 to                  2 shut down.            
      Ltd                              Apr, 08                                       
      Texas, U.S.                                                                    

      Flint Hills Corpus         U     Apr 18, 08   300,000  Sulfur recovery unit shut
      Christi                            to                  for unplanned           
      Koch Industries Inc              Apr, 08               maintenance.            
      Texas, U.S.                                                                    

      Valero Norco St            N     Apr, 08      190,000  FCC runs cut amid       
      Charles                            to                  slumping margins.       
      Valero Energy Corp               May, 08                                       
      Louisiana, U.S.                                                                

      BP Cherry Point            P     Apr 15, 08   232,000  Cokers, reformers shut  
      BP PLC                             to                  mid-April to mid-May in 
      Washington, U.S.                 May 19, 08   planned maintenance. Two
                                                                             cokers and two reformers
                                                                             involved.
      Only one unit will be down at a time. 
                                                              Reformer restart confirmed.              

      Wynnewood OK               P     Apr, 08       70,000  Shutdown to expand      
      Gary-Williams Energy               to                  capacity to 70,000      
      Co                               May 15, 08            barrels a day. Restart  
      Oklahoma, U.S.                                         confirmed May 13.       

      Shell Deer Park            U     Apr 14, 08   340,000  Coker, sulfur recovery  
      Royal Dutch Shell                  to                  unit faults reduce      
      PLC, Petroleos                   May 07, 08        refinery runs. Normal operations  
      Mexicanos                                              estimated for May 5.
      Texas, U.S.                                                              

      Conoco Rodeo               N     Apr 14, 08    76,000  Partial shutdown after  
      ConocoPhillips                     to                  unspecified malfunction.
      California, U.S.                 Apr, 08               Conoco said production not affected.           

      Cenex Laurel               P     Apr 14, 08    55,000  Coker unit enters into  
      CHS Inc                            to                  production.             
      Montana, U.S.                    Apr 15, 08                                    

      Exxon Mobil Torrance       P     Apr 12, 08   155,000  Alkylation unit shut for
      Exxon Mobil Corp                   to                  planned maintenance.    
      California, U.S.                 Apr 30, 08                                    

      Marathon Catlettsburg      N     Apr 11, 08   239,000  FCC shut after fire in  
      Marathon Oil Corp,                 to                  electrical substation.  
      Ashland Inc                      Apr 21, 08            Restart confirmed.      
      Kentucky, U.S.                                                                 

      BP Carson                  N     Apr 11, 08   265,500  Hydrocracker shut after 
      BP PLC                             to                  flash fire. Restart     
      California, U.S.                 Apr 14, 08            confirmed.              

      Total Port Arthur          P     Apr 10, 08   240,000  Catalyst change to      
      Total SA                           to                  unspecified unit. Partial
      Texas, U.S.                      Apr, 08               shutdown.               

      ConocoPhillips Los         P     Apr 09, 08   147,000  CDU, hydrocracker, cokerAngeles                            to                  maintenance. Work to be 
      ConocoPhillips                   May 23, 08        completed in May, ConocoPhillips said.      
      California, U.S.                                      

      Sunoco Marcus Hook         N     Apr 08, 08   175,000  Full shutdown after power
      Sunoco Inc                         to                  failure. Resart sequence
      Pennsylvania, U.S.               Apr 10, 08            confirmed.              

      Alon Big Spring            N     Apr 07, 08    70,000  CDU shut after fire in  
      Alon Israel Oil Co                 to                  tank farm. Restart      
      Ltd                              Apr 08, 08            confirmed.              
      Texas, U.S.                                                                    

      Exxon Mobil Torrance       N     Apr 04, 08   155,000  Hydrotreater fire shuts 
      Exxon Mobil Corp                   to                  units. Unit restarted   
      California, U.S.                 Apr 06, 08            April 6.                

      Valero Benicia             U     Apr 03, 08   153,000  Hydrocracker shut because
      Valero Energy Corp                 to                  of leak. Restart        
      California, U.S.                 Apr 14, 08            confirmed.              

      Valero Houston             N     Apr 01, 08    90,000  Alkylation unit shut    
      Valero Energy Corp                 to                  after substation fire.  
      Texas, U.S.                      Apr 02, 08                                    

      Valero Delaware City       P     Mar 29, 08   190,200  Coker shut for 37 days  
      Valero Energy Corp                 to                  from late March to May  
      Delaware, U.S.                   May 27, 08            27. Restart confirmed.  

      Valero Wilmington          N     Mar 28, 08   135,000  FCC, alkylation shut    
      Valero Energy Corp                 to                  after leak. Unit restart
      California, U.S.                 Apr 06, 08            confirmed.              

      Valero Port Arthur         N     Mar 27, 08   325,000  Coker, hydrocracker shut
      Valero Energy Corp                 to                  after power failure.    
      Texas, U.S.                      Mar 31, 08            Units restarted March 31.

      Conoco Santa Maria         P     Mar 26, 08    44,000  Full shutdown because of
      ConocoPhillips                     to                  power failure. Conoco   
      California, U.S.                 Mar 28, 08            says refinery restarts 3/28.                   

      PEMEX Cardenas             P     Mar 24, 08   190,000  HDD-NPI gasoline unit   
      Minatitlan                         to                  shut for upgrade. Restart
      Petroleos Mexicanos              Apr 07, 08            scheduled for first week
      Mexico                                                 of April.               

      Paramount                  P     Mar 24, 08    55,000  CDUs shut for 24-hours  
      Alon USA Energy Inc                to                  planned maintenance to  
      California, U.S.                 Mar 25, 08            replace an amine boiler.
                                                            Two units idled         

      LyondellBasell             U     Mar 21, 08   287,000  FCC shut for unplanned  
      Houston                            to                  maintenance. Refinery to
      Lyondell Chemical Co             Apr 29, 08     operate at reduced rates
      Texas, U.S.                                            during repairs. Shutdown
                                                                 had been planned to end  
                                                                in mid-April. Restart confirmed.              

      United Warren              N     Mar 20, 08    65,000  Vacuum distillation fire
      United Refining Co                 to                  cuts production. Normal 
      Pennsylvania, U.S.               Mar 23, 08            operations confirmed March 23.               

      Valero Corpus Christi      N     Mar 19, 08   110,000  FCC shut week of March 17
      East                               to                  on poor margins, Valero 
      Valero Energy Corp               May 19, 08     said. Restart process   
      Texas, U.S.                                            began mid May.          

      Valero Delaware City       U     Mar 17, 08   190,200  FCC rates reduced to    
      Valero Energy Corp                 to                  repair boiler.          
      Delaware, U.S.                   Mar 24, 08                                    

      Valero Quebec City         P     Mar, 08      215,000  CDU maintenance to cut  
      Valero Energy Corp                 to                  output by 50,000 bbl/day
      Quebec, Canada                   May, 08               for about 42 days. Unit 
                                                            restart confirmed.      

      Petro-Canada Montreal      P     Mar 15, 08   105,210  CDU shut for one week   
      Petro-Canada                       to                  starting mid-March, FCC 
      Quebec, Canada                   Apr 30, 08            closed for six weeks.   

      Motiva Convent             P     Mar, 08      235,000  Hydrocracker shutdown.  
      Motiva Enterprises                 to                  Restart confirmed.      
      LLC                              Apr 23, 08                                    
      Louisiana, U.S.                                                                

      Conoco Wood River          P     Mar, 08      306,000  FCC maintenance shutdown.
      EnCana Corp,                       to                                          
      ConocoPhillips                   Apr 09, 08                                    
      Illinois, U.S.                                                                 

      Exxon Mobil Beaumont       P     Mar 13, 08   363,100  FCCU maintenance will   
      Exxon Mobil Corp                   to                  cause flaring from March
      Texas, U.S.                      May 15, 08            13 to May 15.           

      Marathon Robinson          P     Mar 11, 08   204,000  Turnaround for planned  
      Marathon Oil Corp,                 to                  maintenance and repairs,
      Ashland Inc                      Apr 30, 08            and the refinery capacity
      Illinois, U.S.                                         is now up to 204,000 bbls a day
      ,
                                                            a company pokeswoman said. Restart confirmed.              

      Tesoro Martinez            P     Mar 10, 08   166,000  Delayed coking unit to be
      Tesoro Corp                        to                  installed during late in
      California, U.S.                 Qtr 1, 08             the first quarter 2008. 

      Exxon Mobil Baytown        P     Mar 09, 08   563,000  FCCU 3 C Boiler shut down
      Exxon Mobil Corp                   to                  during planned          
      Texas, U.S.                      Apr 14, 08            maintenance.            

      Shell Canada Scotford      P     Mar 07, 08   100,000  Runs cut because of lack
      Royal Dutch Shell PLC              to                  of feedstock. Normal    
      Alberta, Canada                  Mar 17, 08            operations confirmed March 17.               

      Marathon Detroit           P     Mar 05, 08   100,000  Full shutdown for planned
      Marathon Oil Corp,                 to                  maintenance. Completion 
      Ashland Inc                      May, 08               of restart confirmed.   
      Michigan, U.S.                                                                 

      Valero Delaware City       P     Mar, 08      190,200  Coker 50,000 bbl/day shut
      Valero Energy Corp                 to                  for 37-days planned     
      Delaware, U.S.                   Apr, 08               maintenance during March/April 2008.       

      Valero Memphis             P     Mar, 08      190,000  FCCU 69,000 bbl/day shut
      Valero Energy Corp                 to                  down for 15-days planned
      Tennessee, U.S.                  Mar 20, 08            maintenance. Unit restart
                                                            confirmed March 26.     

      Big West Oil               N     Mar 04, 08    68,000  Coker shut after a power
      Bakersfield                        to                  outage affected “Area  
      Flying J Oil & Gas               Mar, 08               3” About 500 pounds of 
      Inc                                                    sulfur dioxide was      
      California, U.S.                                       released. An unspecified
                                                            unit was partially shut 
                                                            down.                   

      Valero Corpus Christi      P     Mar 04, 08   110,000  Fire shut a diesel      
      East                               to                  hydrogen desulfurization
      Valero Energy Corp               Mar 10, 08            unit in Complex 1 of the
      Texas, U.S.                                            refinery’s west plant.  

      Suncor Commerce City       P     Mar 03, 08    31,000  Planned maintenance cut 
      (VLO)                              to                  total capacity 40       
      Suncor Energy Inc                Mar 21, 08            percent, a Suncor       
      Colorado, U.S.                                         spokesman said.         

      Suncor Commerce City       P     Mar 03, 08    62,000  Planned maintenance cut 
      Suncor Energy Inc                  to                  total output 40 percent,
      Colorado, U.S.                   Mar 21, 08            a Suncor spokesman said.

      Frontier El Dorado         P     Mar 01, 08   112,000  CDU shut for 38 days of 
      Frontier Oil Corp                  to                  maintenance and         
      Kansas, U.S.                     Apr 08, 08            installation of new     
                                                            vacuum tower. Unit      
                                                            restart confirmed.      

      Imperial Oil               U     Mar, 08      184,000  Runs cut after fault in 
      Strathcona                         to                  gasoline unit led to fuel
      Exxon Mobil Corp                 Apr 06, 08            shortates in Western    
      Alberta, Canada                                        Canada. Restart of unit 
                                                            confirmed.              

      Citgo Corpus Christi       P     Mar 01, 08   156,000  Sulfur recovery unit,   
      Petroleos de                       to                  mixed distillate        
      Venezuela SA                     Apr, 08               hydrotreater and coker  
      Texas, U.S.                                            effective March 1, 2008 
                                                            at West Plant. East plant
                                                            CDU shutdown and vacuum 
                                                            maintenance. SRU started
                                                            as of April 1. Coker as 
                                                            of April 8. CDU and VDU 
                                                            restarted as of April 10

      BP Texas City              P     Mar, 08      470,000  Alkylation unit (45,000 
      BP PLC                             to                  b/d) restarts April 14  
      Texas, U.S.                      Mar 14, 08            after maintenance. Second
                                                            alkylation unit of 22,000
                                                            then to be taken out of 
                                                            service for repairs.    

      Conoco Ponca City          P     Feb, 08      187,000  FCCU restarted March 15 
      ConocoPhillips                     to                  after weeks of planned  
      Oklahoma, U.S.                   Mar 15, 08            maintenance.            

      Valero Benicia             U     Feb, 08      153,000  FCC of 72,000 bbl/day   
      Valero Energy Corp                 to                  shut for unplanned      
      California, U.S.                 Mar, 08               repairs on Feb. 28, 2008.
                                                            2008.                   

      Valero Benicia             U     Feb 28, 08   153,000  FCCU leak forced Valero 
      Valero Energy Corp                 to                  to shut the unit for    
      California, U.S.                 Mar 01, 08            unplanned repairs.      

      Pasadena                   N     Feb 27, 08   106,500  Full shutdown Feb. 27   
      Nationale A                        to                  after a “complete power
      Portefeuille                     Mar 05, 08            failure. FCCU shut down 
      Texas, U.S.                                            following a power outage.

      Valero Norco St            P     Feb 21, 08   190,000  FCCU unit shut down about
      Charles                            to                  2/21/08, reducing       
      Valero Energy Corp               Mar 12, 08            production by 100,000   
      Louisiana, U.S.                                        bbl/day for 20 days.    

      Pasadena                   U     Feb 21, 08   106,500  FCCU shut down for      
      Nationale A                        to                  specific repairs.       
      Portefeuille                     Feb 22, 08                                    
      Texas, U.S.                                                                    

      Exxon Mobil Beaumont       N     Feb 20, 08   363,100  No. 5 Coke drum shut to 
      Exxon Mobil Corp                   to                  repair a leak on Feb. 20,
      Texas, U.S.                      Feb 28, 08            2008, and resumed       
                                                            operation on Feb. 28.   

      Conoco Sweeny              P     Feb 19, 08   216,000  Regenerative thermal    
      Petroleos de                       to                  oxidizer (RTO) which    
      Venezuela SA,                    Feb 20, 08            controls vapors from the
      ConocoPhillips                                         Wasterwater Treater unit
      Texas, U.S.                                            shut for maintenance.   Citgo Corpus Christi       P     Feb 18, 08   156,000  Unibon unit shut for    
      Petroleos de                       to                  planned maintenance. It’s
      Venezuela SA                     Feb 24, 08            also known as a gasoil  
      Texas, U.S.                                            hydrotreater.           

      Tesoro Kapolei             N     Feb 16, 08    95,000  Full shutdown after fire.
      Tesoro Corp                        to                  Units restarted Feb. 18 
      Hawaii, U.S.                     Feb 18, 08                                    

      Hovensa St. Croix          P     Feb 14, 08   495,000  Planned maintenance. The
      Petroleos de                       to                  two largest crude units 
      Venezuela SA, Hess               Mar, 08               were not shut.          
      Corp                                                                           
      US Virgin Islands,                                                             
      U.S.                                                                           

      Total Port Arthur          P     Feb 13, 08   240,000  Reformer shut for planned
      Total SA                           to                  maintenance; and work   
      Texas, U.S.                      Feb 29, 08            should be finished in a 
                                                            couple weeks.           

      Sunoco Philadelphia        N     Feb 13, 08   330,000  Power cut shut          
      Sunoco Inc                         to                  unspecified units.      
      Pennsylvania, U.S.               Feb 13, 08                                    

      Delek LaGloria             N     Feb 12, 08    58,000  Sulfur recovery unit shut
      Delek US Holdings Inc              to                  down after a mechanical 
      Texas, U.S.                      Feb, 08               upset.                  

      Shell Canada Scotford      N     Feb 12, 08   100,000  Runs cut because of     
      Royal Dutch Shell PLC              to                  reduced supplies from oil
      Alberta, Canada                  Feb 20, 08            sand plant.             

      PEMEX Jaime Salina         N     Feb 12, 08   290,000  Earthquake shuts 26     
      Cruz                               to                  processing plants at its
      Petroleos Mexicanos              Feb 14, 08    alina Cruz refinery.   
      Mexico                                                 Pemex restarted operations after finding
                                                            minimal damage.         

      Conoco Borger              P     Feb 11, 08   146,000  FCC repair to           
      ConocoPhillips,                    to                  electrostatic           
      EnCana Corp                      Mar 03, 08            precipitators on the Unit
      Texas, U.S.                                            29                      

      Flint Hills Corpus         P     Feb 11, 08   300,000  Planned maintenance     
      Christi                            to                  caused flaring.         
      Koch Industries Inc              Feb 21, 08                                    
      Texas, U.S.                                                                    

      Valero Delaware City       N     Feb 10, 08   190,200  Full shutdown after power
      Valero Energy Corp                 to                  cut. Power was restored 
      Delaware, U.S.                   Feb 11, 08            to the crude unit, coker,
                                                            and catalytic cracker,  
                                                            and these units restarted
                                                            on 2/11/08. On 2/25/08, 
                                                            the hydrocracker was the
                                                            last main unit to resume
                                                            operation, Valero said. 

      Lake Charles               N     Feb 10, 08   320,000  Power outage disrupted  
      Petroleos de                       to                  operations.             
      Venezuela SA                     Feb 11, 08                                    
      Louisiana, U.S.                                                                

      Chevron Richmond           P     Feb 07, 08   257,200  Reformers. Major planned
      Chevron Corp                       to                  maintenance scheduled for
      California, U.S.                 Mar, 08               1st Qtr 2008. Two reformer units replaced  
                                                                    during this period.     

      Paramount                  P     Feb 07, 08    55,000  CDUs (two of four) shut;
      Alon USA Energy Inc                to                  refinery is undergoing  
      California, U.S.                 Feb, 08               planned maintenance to  
                                                            improve gasoline yields,
                                                            an Alon spokesman said. 

      ConocoPhillips Los         P     Feb 07, 08   147,000  Sulfur recovery units   
      Angeles                            to                  shut down caused flaring.
      ConocoPhillips                   Feb, 08                                       
      California, U.S.                                                               

      Delek LaGloria             N     Feb 07, 08    58,000  Mechanical failure shut a
      Delek US Holdings Inc              to                  boiler and reduced rates
      Texas, U.S.                      Feb 08, 08            into a fluid catalytic  
                                                            cracking unit           

      Shell Deer Park            N     Feb 05, 08   340,000  Coker (85,000 bbl/day)  
      Royal Dutch Shell                  to                  unit shut down after the
      PLC, Petroleos                   Mar 05, 08            anti-surge valve opened,
      Mexicanos                                              Shell said.             
      Texas, U.S.                                                                    

      Valero Wilmington          P     Feb 05, 08   135,000  FCCU and alkylation unit
      Valero Energy Corp                 to                  shut down for about 10  
      California, U.S.                 Feb 14, 08            days planned maintenance,
                                                            a Valero spokesman said.

      Valero Port Arthur         P     Feb 04, 08   325,000  Coker(105,000 bbl/day)  
      Valero Energy Corp                 to                  maintenance.            
      Texas, U.S.                      Feb 29, 08                                    

      Valero Norco St            P     Feb, 08      190,000  CDU maintenance to cut  
      Charles                            to                  about 100k bbl/day for 20
      Valero Energy Corp               Feb, 08               days.                   
      Louisiana, U.S.                                                                

      Wynnewood OK               N     Feb 01, 08    70,000  Fire caused by a leak in
      Gary-Williams Energy               to                  a depropanizer unit. The
      Co                               Feb 01, 08            fire was extinguished and
      Oklahoma, U.S.                                         refinery rates weren’t  
                                                            reduced, a company      
                                                            spokesman said.         

      Tesoro Anacortes           P     Jan 31, 08   108,000  Planned maintenance     
      Tesoro Corp                        to                                          
      Washington, U.S.                 Feb, 08                                       

      Conoco Wood River          P     Jan 31, 08   306,000  Flare gas recovery      
      EnCana Corp,                       to                  compressor shut for     
      ConocoPhillips                   Jan 31, 08            repairs.This will not   
      Illinois, U.S.                                         affect production.      

      BP Texas City              N     Jan 30, 08   470,000  FCC (120,000 bbl/day)   
      BP PLC                             to                  restarted after a Jan. 30
      Texas, U.S.                      Mar 07, 08            electrical fault. Crude 
                                                            unit (250,000 bbl/day   
                                                            pipestill 3B) restarted 
                                                            March 7 after shutting  
                                                            down following Hurricane
                                                            Katrina in 2005.        

      Valero Aruba               N     Jan 25, 08   275,000  Full shutdown after     
      Valero Energy Corp                 to                  vacuum tower fire.      
      Aruba                            May 28, 08            Partial operations      
                                                            resumed by Feb. 5. Vacuum
                                                            crude distillation unit 
                                                            restarted May 28.       

      Big West Oil               P     Jan, 08       68,000  Planned maintenance on an
      Bakersfield                        to                  unknown unit is scheduled
      Flying J Oil & Gas               Feb, 08               to last from 7 to 10 days
      Inc                                                    during late Jan. 2008, a
      California, U.S.                                       Flying J manager said.  

      Total Port Arthur          N     Jan 24, 08   240,000  Sulfur recovery unit went
      Total SA                           to                  down causing an emission
      Texas, U.S.                      Jan 24, 08            release. The shell claus
                                                            off-gas treating unit was
                                                            restarted as soon as    
                                                            possible, Total said.   

      LyondellBasell             P     Jan 23, 08   287,000  Aromatics unit shut by  
      Houston                            to                  fire ahead of planned   
      Lyondell Chemical Co             Mar 20, 08            maintenance scheduled to
      Texas, U.S.                                            begin the week of Jan.  
                                                            28, a LyondellBasell    
                                                            Industries spokeswoman said.                   

      Suncor Sarnia              P     Jan 23, 08    80,000  Runs cut 30% because of 
      Suncor Energy Inc                  to                  fault in new diesel     
      Ontario, Canada                  Jan, 08               hydrotreater, lack of   
                                                            hydrogen supply.        

      Valero Corpus Christi      N     Jan 23, 08   110,000  Vapor recovery compressor
      East                               to                  located on the No. 4    
      Valero Energy Corp               Jan 29, 08            crude unit shut at      
      Texas, U.S.                                            Complex 7 on Jan. 23    
                                                            after an electrical short circuit.                

      Total Port Arthur          P     Jan 21, 08   240,000  Refinery planned        
      Total SA                           to                  maintenance             
      Texas, U.S.                      Mar 08, 08                                    

      Conoco Borger              P     Jan 21, 08   146,000  Hydrogen desulfurization
      ConocoPhillips,                    to                  unit shut down Jan. 21 to
      EnCana Corp                      Jan 26, 08            repair a leak is expected
      Texas, U.S.                                            to return to normal with
                                                            a week. It will have    
                                                            minimal effect on       
                                                            production.             

      Exxon Mobil Baytown        P     Jan 18, 08   563,000  Delayed Coking unit shut
      Exxon Mobil Corp                   to                  for planned maintenance.
      Texas, U.S.                      Mar 14, 08                                    

      Shell Deer Park            P     Jan 17, 08   340,000  FCC, gasoline           
      Royal Dutch Shell                  to                  hydrotreater, alkylation
      PLC, Petroleos                   Mar 05, 08            facility and three sulfur
      Mexicanos                                              recovery plants shut    
      Texas, U.S.                                            during maintenance.     

      Motiva Port Arthur         U     Jan 14, 08   285,000  Waste-heat boiler       
      Motiva Enterprises                 to                  shutdown for about 20   
      LLC                              Feb 03, 08            days to repair a leak. A
      Texas, U.S.                                            scrubber will be        
                                                            bypassed, causing flaring
                                                            through Feb. 3.         

      BP Texas City              N     Jan 14, 08   470,000  Hydrocracker            
      BP PLC                             to                  (ultracracker) explosion
      Texas, U.S.                      Jan, 08               kills one worker.       

      Exxon Mobil Baytown        P     Jan 12, 08   563,000  CDU maintenance Jan. 12 
      Exxon Mobil Corp                   to                  to March 31. Coker      
      Texas, U.S.                      Mar 31, 08            restarted March 14. An  
                                                            FCCU also repaired while
                                                            maintenance performed on the coker.              

      BP Carson                  P     Qtr 1, 08    265,500  FCC Upgrade to          
      BP PLC                             to                  electrostatic precipitator.          
      California, U.S.                 Mar 28, 08        Several units to be upgraded in 
                                                            2008 to cut sulfur in gasoline, diesel. Sulfur
                                                            Plant, alkylation repairs also planned.           

      Valero Aruba               N     Jan 08, 08   275,000  Full refinery shutdown  
      Valero Energy Corp                 to                  after a power disruption
      Aruba                            Jan 15, 08            on Jan. 8.              

      Marathon Garyville         P     Jan, 08      275,000  FCC shut down for planned
      Marathon Oil Corp,                 to                  maintenance sometime    
      Ashland Inc                      Feb, 08               during the week of Jan. 
      Louisiana, U.S.                                        7. Timeline for restart 
                                                            not detailed.           

      Alon Big Spring            P     Jan 07, 08    70,000  Hydrotreater 22,000     
      Alon Israel Oil Co                 to                  bbl/day, Reformer 21,000
      Ltd                              Jan 14, 08            bbl/day, Gasoil         
      Texas, U.S.                                            hydrotreater 6,500      
                                                            bbl/day, jet fuel unit  
                                                            4,500 bbl/day shut for  
                                                            maintenance Jan. 7.     

      Valero Corpus Christi      P     Jan, 08      110,000  CDU maintenance to cut  
      East                               to                  40,000 bbl/day for 14   
      Valero Energy Corp               Jan, 08               days during January at  
      Texas, U.S.                                            its west plant.         

      Exxon Mobil Baton          P     Jan 04, 08   488,600  FCC, alkylation units   
      Rouge                              to                  turnaround planned to   
      Exxon Mobil Corp                 Feb, 08               last several weeks and  
      Louisiana, U.S.                                        end around the end of   
                                                            February, ExxonMobil    
                                                            said.                   

      Chalmette LA               P     Jan 04, 08   184,000  FCCU, alkylation unit and
      Petroleos de                       to                  other units will be     
      Venezuela SA, Exxon              Feb 27, 08            undergoing planned      
      Mobil Corp                                             maintenance until the end
      Louisiana, U.S.                                        of February.            

      Sunoco Inc Eagle           P     Qtr 1, 08    150,000  CDU turnaround, brought 
      Point Refinery                     to                  forward from second half
      Sunoco Inc                       Qtr 1, 08             of year.                
      New Jersey, U.S.                                                               

      Sunoco Toledo              P     Qtr 1, 08    150,000  Planned maintenance will
      Sunoco Inc                         to                  reduce production 2.5   
      Ohio, U.S.                       Qtr 1, 08             million barrels during  
                                                            Qtr 1, 08.              

      Sunoco Philadelphia        P     Qtr 1, 08    330,000  CDU, FCC unit maintenance
      Sunoco Inc                         to                  completed.              
      Pennsylvania, U.S.               Qtr 1, 08                                     

      BP Whiting                 P     Dec 27, 07   420,000  CDU, 95,000 bbl/day shut
      BP PLC                             to                  for planned maintenance.
      Indiana, U.S.                    Mar 22, 08                                    

      Paramount                  N     Dec 19, 07    55,000  Power outage shut part of
      Alon USA Energy Inc                to                  the 55,000-barrel-a-day 
      California, U.S.                 Dec 21, 07            section of Alon’s 90,000
                                                            barrel-a-day Paramount, 
                                                            CA refining complex. The
                                                            entire refinery will resume on Dec. 21, a    
                                                            company spokesman said. 

      Conoco Borger              P     Dec 18, 07   146,000  Electrostatic           
      ConocoPhillips,                    to                  precipitators,(air      
      EnCana Corp                      Dec 28, 07      filters) on Borger’s FCC unit.           
      Texas, U.S.                                            are scheduled for maintenance       
                                                                 from Dec. 18 to Dec. 28, Conoco said.

      Frontier Cheyenne          N     Dec 15, 07    52,000  Coking Unit down        
      Frontier Oil Corp                  to                  10,000bbls/day due to fire.  
      Wyoming, U.S.                    Jan 11, 08       Refinery running at
                                                            25,000bbls/day until    
                                                            12/16/2007, then 42,000bbls until coking 
                                                            unit is fixed. Feed was returned to the coking  
                                                            unit on Jan. 11.        

      Exxon Mobil Beaumont       N     Dec 11, 07   363,100  Reformer resumed output 
      Exxon Mobil Corp                   to                  after a leak in a       
      Texas, U.S.                      Dec 15, 07            hydrogen injection point
                                                            started a fire forcing  
                                                            the plant to reduce     
                                                            operating rates.        

      Exxon Mobil Torrance       U     Dec 11, 07   155,000  Two boilers shut down for
      Exxon Mobil Corp                   to                  unplanned maintenance.  
      California, U.S.                 Dec 11, 07            Other units are         
                                                            operating, per a        
                                                            state-run website. The  
                                                            boillers, which make    
                                                            steam for the refinery, 
                                                            restarted the same day, 
                                                            ExxonMobil said.        

      Syncrude Upgrader          N     Dec 05, 07    84,000  Coker 8-3 unit shut by  
      Canadian Oil Sands                 to                  fire, cuts output       
      Trust, Imperial Oil              Dec 18, 07            75,000-bbl/day. The unit
      Resources, Petro                                       resumed operation on Dec.
      Canada, ConocoPhilips                                  18.                     
      Oil Sands Partnership                                                          
      II, Nexen Oil Sands                                                            
      Partnership, Mocal                                                             
      Energy Ltd, Murphy                                                             
      Oil Co Ltd                                                                     
      Alberta, Canada                                                                

      BP Texas City              N     Dec 04, 07   470,000  Reformer was shutdown   
      BP PLC                             to                  because of a gas        
      Texas, U.S.                      Dec, 07               compressor tripped      
                                                            following a Dec. 2 power
                                                            outage.                 

      BP Texas City              N     Dec 04, 07   470,000  A ultracracker          
      BP PLC                             to                  (hydrocracker) was      
      Texas, U.S.                      Dec 08, 07            shutdown because of a gas
                                                            compressor tripped      
                                                            following a Dec. 2 power
                                                            outage. The ultracracker
                                                            restart will last from  
                                                            12/4-12/8/07.           

      Valero Texas City          N     Dec 02, 07   230,000  FCCU, 85,000-bbl/day,   
      Valero Energy Corp                 to                  resumed operations Dec  
      Texas, U.S.                      Dec 19, 07            11. A crude unit started
                                                            Dec. 19. Operations     
                                                            returned to normal by   
                                                            Jan. 9, 2008, said Bill 
                                                            Day, a company spokesman
                                                            said.                   

      BP Texas City              N     Dec 02, 07   470,000  Gas compressor tripped  
      BP PLC                             to                  following a Dec. 2 power
      Texas, U.S.                      Dec 02, 07            outage.                 

      Valero Memphis             U     Nov 21, 07   190,000  FCCU shut for 10 days   
      Valero Energy Corp                 to                  unplanned repairs       
      Tennessee, U.S.                  Nov 30, 07            resulting in a loss of  
                                                            65,000 bbls/day gasoline
                                                            and 35,000 bbls/day     
                                                            distillate fuel.        

      Shell Canada Scotford      N     Nov 19, 07   100,000  Upgrader’s residue      
      Royal Dutch Shell PLC              to                  hydroconversion unit leak
      Alberta, Canada                  Dec 20, 07            caused a fire. The      
                                                            Scotford upgrader resumed
                                                            limited heavy crude     
                                                            production on the       
                                                            atmospheric and vacuum  
                                                            unit on Dec. 20. The    
                                                            upgrader resumed normal 
                                                            operation by Jan 8, 2008
                                                            Shell said.             

      Flint Hills Corpus         P     Nov 18, 07   300,000  Crude unit and distillate
      Christi                            to                  hydrotreater shut for   
      Koch Industries Inc              Nov 25, 07            about seven days planned
      Texas, U.S.                                            maintenance.            

      Conoco Sweeny              U     Nov 15, 07   216,000  Desulfurization unit, or
      Petroleos de                       to                  RTO, regenerative thermal
      Venezuela SA,                    Nov 16, 07            oxidizer shut for repairs
      ConocoPhillips                                         that will result in     
      Texas, U.S.                                            venting about 36 pounds 
                                                            of benzene during a     
                                                            six-hour period ending 2
                                                            p.m. on Nov. 16., per   
                                                            state filing.           

      Alon Big Spring            N     Nov 13, 07    70,000  Crude unit shut down for
      Alon Israel Oil Co                 to                  a few hours following a 
      Ltd                              Nov 14, 07            power outage, the company
      Texas, U.S.                                            said.                   

      Valero Port Arthur         N     Nov 08, 07   325,000  Fire shut down a kerosene
      Valero Energy Corp                 to                  hydrotreater Nov. 8, the
      Texas, U.S.                      Nov 27, 07            unit restarted by 11/27.
                                                            However, a second       
                                                            distillate hydrotreater 
                                                            remains down. Refinery is
                                                            operating at about 80   
                                                            percent, Valero said.   

      Alon Big Spring            N     Nov 08, 07    70,000  Sulfur recovery unit shut
      Alon Israel Oil Co                 to                  by leak. Repairs are    
      Ltd                              Nov 08, 07            expected to be completed
      Texas, U.S.                                            in 12 hours.            

      Motiva Convent             N     Nov 06, 07   235,000  Crude unit shut by fire,
      Motiva Enterprises                 to                  resumed normal operations
      LLC                              Nov 12, 07            Nov. 12, the company    
      Louisiana, U.S.                                        said.                   

      Exxon Mobil Torrance       P     Nov 05, 07   155,000  FCCU and alkylation unit
      Exxon Mobil Corp                   to                  resumed normal operations
      California, U.S.                 Dec 31, 07            after three weeks planned
                                                            maintenance, Exxon said.

      Tesoro Kapolei             N     Nov 04, 07    95,000  Full shutdown after a   
      Tesoro Corp                        to                  power failure. A reformer
      Hawaii, U.S.                     Dec, 07               shutdown following this 
                                                            incident returned to    
                                                            service during the week 
                                                            of Dec. 20, Tesoro said.

      Valero Wilmington          N     Nov 02, 07   135,000  Sulfur recovery unit shut
      Valero Energy Corp                 to                  briefly following sulfur
      California, U.S.                 Nov 02, 07            dioxide release.        

      Valero Wilmington          P     Nov 01, 07   135,000  FCCU 54,000 bbl/day unit
      Valero Energy Corp                 to                  resumed operation, a    
      California, U.S.                 Jan, 08               company spokesman said. 

      Conoco Borger              N     Oct 30, 07   146,000  Coker operating at      
      ConocoPhillips,                    to                  reduced rate, while wet 
      EnCana Corp                      Nov 03, 07            gas compressor undergoes
      Texas, U.S.                                            repairs                 

      Delek LaGloria             N     Oct 29, 07    58,000  Sulfur recovery unit shut
      Delek US Holdings Inc              to                  down after a steam leak 
      Texas, U.S.                      Nov 02, 07                                    

      Big West Oil               N     Oct 27, 07    68,000  Hydrocracker shut after 
      Bakersfield                        to                  an Oct. 27 power outage.
      Flying J Oil & Gas               Oct 30, 07            Restarted on Oct. 30    
      Inc                                                                            
      California, U.S.                                                               

      Shell Deer Park            N     Oct 27, 07   340,000  Hydrotreater shut after 
      Royal Dutch Shell                  to                  fire, refinery partially
      PLC, Petroleos                   Oct 30, 07            shut down.              
      Mexicanos                                                                      
      Texas, U.S.                                                                    

      Shell Deer Park            P     Oct 22, 07   340,000  MTBE unit shut to flare 
      Royal Dutch Shell                  to                  chemicals from 10/22 to 
      PLC, Petroleos                   Jan 19, 08            1/19, per report filed  
      Mexicanos                                              with state regulators.  
      Texas, U.S.                                                                    

      Total Port Arthur          P     Oct 22, 07   240,000  Flare Gas Recovery      
      Total SA                           to                  Compressor (C-401) is   
      Texas, U.S.                      Nov 12, 07            undergoing planned      
                                                            maintenance.            

      Conoco Borger              P     Oct 20, 07   146,000  Partial shutdown of an  
      ConocoPhillips,                    to                  FCCU for planned        
      EnCana Corp                      Nov 24, 07            maintenance             
      Texas, U.S.                                                                    

      Conoco Sweeny              P     Oct 20, 07   216,000  No. 3 FCCU restarted and
      Petroleos de                       to                  is expected to be fully 
      Venezuela SA,                    Nov 05, 07            operational by the end of
      ConocoPhillips                                         the first week in Nov.  
      Texas, U.S.                                            2007                    

      Exxon Mobil Billings       N     Oct 17, 07    62,200  Hydrocracker shut by    
      Exxon Mobil Corp                   to                  explosion, fire at the  
      Montana, U.S.                    Mar, 08               Lockwood refinery. The  
                                                            hydrocracker went back  
                                                            into service by about   
                                                            Dec. 15, and was up to  
                                                            full pressure by about  
                                                            Jan. 1, 2008, the company
                                                            said.                   

      Valero Port Arthur         P     Oct 13, 07   325,000  Planned Maintenance     
      Valero Energy Corp                 to                                          
      Texas, U.S.                      Oct 28, 07                                    

      Exxon Mobil Beaumont       N     Oct 12, 07   363,100  On Oct. 12, FCC 112,000 
      Exxon Mobil Corp                   to                  bbl/day unit shut down  
      Texas, U.S.                      Nov 18, 07            for unplanned repairs.  
                                                            Confirmed restart on 11/8

      Chevron El Segundo         P     Oct 10, 07   260,000  Planned turnaround      
      Chevron Corp                       to                  maintenance will last two
      California, U.S.                 Dec 10, 07            months.                 

      Shell Canada Montreal      P     Oct 10, 07   130,000  Refinery is returning to
      East                               to                  normal processing rates 
      Royal Dutch Shell PLC            Nov 20, 07            after an extended       
      Quebec, Canada                                         scheduled turnaround.   
                                                            Maximium crude oil      
                                                            processing capacity is  
                                                            130,000 barrels a day.  

      Valero Benicia             P     Oct 09, 07   153,000  Coker                   
      Valero Energy Corp                 to                                          
      California, U.S.                 Nov 08, 07                                    

      Valero Paulsboro           P     Oct 09, 07   195,000  Crude                   
      Valero Energy Corp                 to                                          
      New Jersey, U.S.                 Nov 07, 07                                    

      Shell Martinez             N     Oct 09, 07   165,000  Shell shut a hydrotreater
      Royal Dutch Shell PLC              to                  after an “operational   
      California, U.S.                 Oct 10, 07            upset” on Oct. 9, The   
                                                            unit is back up and     
                                                            resumed normal operations
                                                            on Oct. 10              

      ConocoPhillips Los         N     Oct 08, 07   147,000  Hydrocracker            
      Angeles                            to                                          
      ConocoPhillips                   Oct 18, 07                                    
      California, U.S.                                                               

      Port Reading               N     Oct 08, 07    65,000  Problem in wet gas      
      Hess Corp                          to                  compressor forced Hess to
      New Jersey, U.S.                 Oct 10, 07            shut the refinery on Oct.
                                                            8. The FCCU will start  
                                                            processing fuel by noon 
                                                            on Oct. 10, a Hess      
                                                            spokesman said.         

      BP Carson                  P     Oct 06, 07   265,500  Hydrocracker            
      BP PLC                             to                                          
      California, U.S.                 Nov 02, 07                                    

      Valero Aruba               N     Oct 05, 07   275,000  Power failure on Oct. 5 
      Valero Energy Corp                 to                  forced the entire       
      Aruba                            Oct 24, 07            refinery to shut down. On
                                                            Oct. 16, some units     
                                                            restarted, and all units
                                                            returned to normal on   
                                                            Oct. 24, Valero said.   

      BP Carson                  P     Oct 04, 07   265,500  Coker and crude unit    
      BP PLC                             to                  undergoing planned      
      California, U.S.                 Oct 31, 07            maintenance             

      Exxon Mobil Torrance       N     Oct 04, 07   155,000  Hydrogen Unit           
      Exxon Mobil Corp                   to                                          
      California, U.S.                 Oct 04, 07                                    

      ConocoPhillips Los         N     Oct 03, 07   147,000  Refinery                
      Angeles                            to                                          
      ConocoPhillips                   Oct 18, 07                                    
      California, U.S.                                                               

      Suncor Commerce City       P     Oct 02, 07    31,000  Refinery Turnaround Done,
      (VLO)                              to                  Restart Confirmed       
      Suncor Energy Inc                Nov 07, 07                                    
      Colorado, U.S.                                                                 

      North Atlantic N           P     Oct, 07      105,000  Crude unit and vacuum   
      Atlantic                           to                  tower will be started   
      Harvest Energy Trust             Nov, 07               during the beginning of 
      Newfoundland and                                       December, plus or minus a
      Labrador, Canada                                       few days, the company   
                                                            said. Refinery can      
                                                            process up to 115,000   
                                                            bbl/day.                

      Irving Saint John          P     Oct, 07      250,000  Refinery turnaround,    
      Irving Oil Corp                    to                  including maintenance of
      Newfoundland and                 Nov, 07               FCC Unit.               
      Labrador, Canada                                                               

      Valero Texas City          P     Oct 01, 07   230,000  FCCU                    
      Valero Energy Corp                 to                                          
      Texas, U.S.                      Nov 12, 07                                    

      Frontier El Dorado         P     Oct, 07      112,000  Alkylation              
      Frontier Oil Corp                  to                                          
      Kansas, U.S.                     Oct, 07                                       

      Marathon Catlettsburg      P     Oct, 07      239,000  Restarted units following
      Marathon Oil Corp,                 to                  several weeks planned   
      Ashland Inc                      Oct 31, 07            maintenance             
      Kentucky, U.S.                                                                 

      _____________________________

      Charles E. Randall
      Independent Carbon & Coke Consultant
      PO Box 73061
      Houston, TX 77273
      Direct: 281-813-2669
      Mobile: 281-813-2669
      Fax: none
      Email: charlierandall01@msn.com

Viewing 0 reply threads
  • You must be logged in to reply to this topic.
2923 Topics 3878 Replies

Coking forum

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Curabitur aliquam venenatis venenatis. Vestibulum tempus malesuada rhoncus.

Open forum