      Suncor Says Reduced Water Withdrawal Wont Cut Output (Update1)

      By Aaron Clark and Robert Tuttle
           Jan. 21, 2008 (Bloomberg)
      Suncor Energy Inc. said production
      from its Fort McMurray, Alberta, oil sands operation wont be
      affected by a reduction in water withdrawals from the Athabasca
      River.
           We withdraw 0.3 percent of Athabasca Rivers annual flow
      so we dont expect this to have impact on our production, Shawn
      Davis, a Suncor spokeswoman, said in a telephone interview.
      Suncors Fort McMurray oil sands produced 235,000 barrels of
      synthetic crude a day in December, Davis said.
           Suncor, Canadian Natural Resources, Syncrude Canada Ltd. and
      Royal Dutch Shell Plcs Albian Sands were ordered to reduce water
      usage from the river because of low water flows,
      said Ogho
      Ikhalo, a spokeswoman for Alberta Environment.
           Syncrude Canada Ltd. spokeswoman Cheryl Robb said its draw
      from the river is minimal.
           I dont know what the impact on production would be, but I
      can tell you that 88 percent of the water we use is from our own
      retaining pond, Robb said.
           The rivers water levels have dipped below the yellow
      warning zone and may increase stress on the aquatic
      ecosystems, according to a statement from Alberta Environment.
           It doesnt really pose a serious constraint on these
      operators because they do have a plan in place for situations
      like this, said Ikhalo.
           The four oil producers can withdraw 6 cubic meters of water
      a second during normal water flows, she said. She did not know
      the reduced withdrawal amount the companies are allowed.
           The river is currently flowing at 118 cubic meters a second,
      down from the 127 cubic meters a second
      , necessary for normal
      withdrawals.
           Telephone calls to Canadian Natural Resources and Shell were
      not immediately returned.

       

Viewing 0 reply threads
  • You must be logged in to reply to this topic.
2923 Topics 3878 Replies

Coking forum

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Curabitur aliquam venenatis venenatis. Vestibulum tempus malesuada rhoncus.

Open forum