Total Pt Arthur Coker Petcoke Production Estimates

Home Forums Coking News: DCU, Upgrader 1.Coker (registered users only) Total Pt Arthur Coker Petcoke Production Estimates

Viewing 0 reply threads
  • Author
    Posts
    • #2048
      basil parmesan
      Participant

      Offline Question: Hey Charlie,
      I’ve got someone asking me what is Total’s Port Arthur coke production? I’ve seen on the internet 730,000tph and over 1,000,000tpy. I figure you probably have the straight scoop.
      Thanks,

      Answer:
      The 730Kmtpy is probably the expected output for this year with startup in 2Q2011. The 1-1.1MM mtpy is what Kinder Morgan has on their May 2011 Terminal presentation (doing handling for Total) and what CemReview Petcoke report has down for expected production capacity. Its 50MBD / 4 drum / Fluor EPC project so I think 1.1MM mtpy is probably conserative and based on design cycle times of 18-24 hours. Total is going crank that baby up (12-16hr cycles) just like every other refinery once crazy WTI differential gets sorted & enough Canadian crude finally makes it gulf coast via P/L (or VZ-Mexico get their acts back together).

      Would appreciate if anyones got any info on what Total’s coker cycle times/ new crude charge & rates/petcoke production will really be with new coker ( Fluor did EPC work) now that is operating.
      The 750kmtpy came from a HydroCarbon Processing Article in August 2011. Previous update was in July & May 2011 after startup at begining of 2Q2011.

Viewing 0 reply threads
  • You must be logged in to reply to this topic.
2923 Topics 3878 Replies

Coking forum

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Curabitur aliquam venenatis venenatis. Vestibulum tempus malesuada rhoncus.

Open forum