      Table Of Asia Refinery Maintenance/Shutdown Schedules

      SINGAPORE -(Dow Jones)- The following table lists recent and upcoming maintenance schedules and outages for oil refineries in Asia. More information will be added as it becomes available. Country Company Location Unit(B/D) Period/Duration
      Australia BP Kwinana part of refinery Sep 30; 1 week
      (137,000)
      China PetroChina Qianguo Whole Refinery Permanent
      China Wepec Dalian RFCC End Sep; 2 weeks
      (3 million*)
      India CPCL Chennai Third of Refinery Jan-Feb; 50 days
      (65,000)
      India MRPL DHDS Feb/Mar 2010; 30 days
      (24,000)
      India IOC Panipat CDU July-Aug 2010; 40-45 days                                    (120,000)
      India HPCL Vizag FCC Nov/Dec; 45 days
      (14,000)
      India HPCL Vizag HDS Dec-Jan; 30 days
      (45,000)
      Indonesia Pertamina Balikpapan CDU Oct; 20-25 days
      (60,000)
      Hydrocracker Mid-Jan; Indefinitely
      (15,000)
      Indonesia Pertamina Plaju CDU Dec; 2 days
      (30,000)
      Indonesia Pertamina Balongan Whole Refinery Late January; 10 days
      (150,000)
      Indonesia Pertamina Balongan RFCC During Week Of Jan 11-17 (NA)
      Indonesia Pertamina Plaju Whole Refinery Late Jan
      (118,000)
      Japan Nippon Oil Marifu CDU Feb 2010; 1 Month
      (127,000)
      Japan Nippon Oil Mizushima No. 2 CDU Mid Jul-End March 2010
      (110,000)
      Japan Taiyo Oil Shikoku No. 1 & 2 CDU Mid Jun, 2010; 2 Months
      (120,000)
      Singapore Shell Bukom Hydrocracker Mid Sep; 2 months
      (34,000)
      S Korea S-Oil Onsan No. 2 RHDS Oct 5-31
      (53,000)
      S Korea S-Oil Onsan No. 3 CDU March 2010; 22 days
      (250,000)
      S Korea S-Oil Onsan No. 1 VRDS March 2010; 30 days
      (52,000)
      S Korea S-Oil Onsan hydrocracker March 2010; 30 days
      (75,000)
      S Korea S-Oil Onsan RFCC June 2010; 30 days
      (73,000)
      S Korea SK Energy Ulsan No. 1 CDU Early Apr-TBA
      (60,000)
      S Korea SK Energy Ulsan No. 2 RFCC July (1 month)
      (60,000)
      S Korea GS Caltex Yeosu No. 1 CDU Apr 2010; 30 days
      (100,000)
      S Korea Hyundai Oilbank Daesan No. 2 CDU Apr 2010; 20 days
      (290,000)
      Taiwan CPC Dalin No. 9 CDU Sep 1-End Feb
      (100,000)
      Taiwan CPC Dalin No. 1 RDS Dec 10-Feb 2
      (30,000)
      Taiwan CPC Dalin No. 6 Reformer Aug 3-Nov 3
      (30,000)
      Taiwan CPC Taoyuan No. 2 CDU Dec 19-Jan 24
      (100,000)
      Taiwan CPC Taoyuan No. 2 Reformer Dec 10; 60 days
      (25,000)
      Taiwan CPC Taoyuan VGH Aug 31-Nov 30
      (20,000)
      Taiwan CPC Taoyuan RFCC Nov 1-Jan 10
      (50,000)
      Taiwan CPC Kaohsiung FCC Oct-Feb
      (25,000)
      Taiwan CPC Kaohsiung No. 2 RDS From March 8 (38-40 days) (30,000)
      Taiwan Formosa Mailiao No. 1 RFCC Oct 8-Nov 14 ’09
      (84,000)
      Taiwan Formosa Mailiao No. 2 RFCC Oct 1-10 ’09
      (84,000) From Mar 2010 (55-60 days)Taiwan Formosa Mailiao No. 1 RDS Oct 1-Nov 2 ’09
      (80,000) From Mar 2010 (35 days)
      Taiwan Formosa Mailiao No. 2 RDS Oct 1-Nov 2 ’09
      (80,000) Oct 2010
      Taiwan Formosa Mailiao No. 1 CDU Mar 21-31 ’10
      (180,000)
      Taiwan Formosa Mailiao No. 2 CDU Sep 23-25 ’09
      (180,000) Oct 1-Nov 5 ’09
      Taiwan Formosa Mailiao No. 3 CDU Mar 1-21 ’10
      (180,000)
      Taiwan Formosa Mailiao Delayed Coker Dec 4-18 ’09
      (36,000)
      Vietnam PetroVietnam Dung Quat whole refinery Aug 18-Oct 1
      (130,000) Dec 22-Jan 13

      Note: B/D – Barrels a day
      N/A – Not available
      TBA – To be announced
      CDU – Crude distillation unit
      FCC – Fluid catalytic cracker
      HDS – Hydrodesulfurizer
      RCC – Residue catalytic cracker
      RFCC – Residual fluid catalytic cracker
      RDS – Residual desulfurizer
      RHDS – Residue hydro desulfurizer
      VRDS – Vacuum residual desulfurizer * – Tons a year

      Keyword search “Table Of Asia Refinery Maintenance” for details of previous refinery outages. (END) Dow Jones Newswires
      01-25-100707ET

Viewing 0 reply threads
  • You must be logged in to reply to this topic.
2923 Topics 3878 Replies

Coking forum

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Curabitur aliquam venenatis venenatis. Vestibulum tempus malesuada rhoncus.

Open forum