      <Here is Bloomberg Update Jan 2009 of the Asia Pacific S/D & Project table – CER>
      ———
      Asian Oil Refinery Shutdowns, Maintenance, Expansion (Table)

      By Nesa Subrahmaniyan and Yuji Okada
           January 8, 2009 (Bloomberg)
      — The following is a table of refinery shutdowns in
      Asia, confirmed by Bloomberg. 

           Shutdown Type: P: Planned, U: Unplanned, N: Non-maintenance

      Refinery                           Shutdown  Capacity                          
      Company                  Period      Type      b/d     Unit Reason             
      ——————————————————————————–
                                     *** AUSTRALIA ***

      BP Kwinana               Oct 29, 08    P      138,000  CDU, FCC, alkylation,   
      BP PLC                     to                          sulfur recovery plant   
                               Dec 29, 08                    shut for repairs. Restart
                                                             confirmed.              

      Caltex Lytton            Qtr 1, 09     P      105,500  Full shutdown for full  
      Caltex Corp                to                          inspection and          
                               Qtr 2, 09                     maintenance in 2009 in  
                                                             four-five year cycle.   

                               Qtr 1, 09     P      105,500  New diesel hydrotreater 
                                 to                          unit to start output in 
                               Qtr 1, 09                     first quarter 2009.     

                               Dec 12, 08    N      105,500  Full shutdown after steam
                                 to                          loss. Units began restart
                               Jan 05, 09                    on 12/13. Full production
                                                             planned for early       
                                                             January.                

                               Qtr 3, 08     P      105,500  CDU, diesel hydrotreater
                                 to                          shut for maintenance in 
                               Qtr 4, 08                     second half of year.    

      Shell Clyde              Nov 30, 08    P       86,000  Full shutdown starting  
      Royal Dutch Shell PLC      to                          end Nov.                
                               N/A                                                   

                                       *** CHINA ***

      CNOOC Huizhou            Qtr 1, 09     P      240,000  New refinery planned to 
      China National Offshore    to                          come on line in 2009.   
      Oil Corp                 Qtr 2, 09                                             

      PetroChina Dushanzi      Aug, 08       P      120,000  Capacity to increase to 
      China National             to                          10 million tons from 6  
      Petroleum Corp           Aug, 08                       million tons a year, with
                                                             the additional capacity 
                                                             scheduled to start in   
                                                             August.                 

      PetroChina Fushun        Oct 10, 08    P      162,000  New CDU, capacity 160,000
      China National             to                          barrels a day, begins   
      Petroleum Corp           Oct, 08                       trial production.       

      Petrochina Lanzhou       Aug 23, 08    P      151,800  CDU, FCC shuts for      
      China National             to                          planned repairs, from   
      Petroleum Corp           Sep 29, 08                    Aug. 23 for 30 to 45    
                                                             days.                   

      Sinopec Hainan           Qtr 4, 09     P      128,700  Full shutdown of the    
      China Petrochemical        to                          160,000 b/d refinery for
      Corp                     Qtr 4, 09                     30 days in 4Q of 2009.  

                               Dec 31, 08    P      128,700  Hydrocracker, capacity  
                                 to                          24,000 b/d, shuts for   
                               Feb 15, 09                    maintenance.            

      Sinopec Maoming          Oct, 09       P      270,000  New wax hydrotreater    
      China Petrochemical        to                          scheduled to begin      
      Corp                     Oct, 09                       operations. Capacity    
                                                             36,000 barrels a day.   

      Sinopec Qilu             Jul 31, 08    P      210,000  CDU                     
      China Petrochemical        to                                                  
      Corp                     Aug 28, 08                                            

      Sinopec Tianjin          Qtr 1, 09     P      100,000  New units to increase   
      China Petrochemical        to                          crude distillation      
      Corp                     Qtr 4, 09                     capacity to 250,000     
                                                             barrels a day scheduled 
                                                             to start in 2009.       

                               Sep 05, 08    P      100,000  100,000 b/d CDU shut for
                                 to                          maintenance.            
                               Nov 06, 08                                            

                                       *** INDIA ***

      Indian Gujarat Koyali    Qtr 1, 10     P      274,000  New diesel hydrotreater 
      Indian Oil Corp Ltd        to                          unit to start.          
                               Qtr 2, 10                                             

                               Aug, 08       P      274,000  CDU. 3.8                
                                 to                          million-tons-a-year     
                               Sep, 08                       (77,000 barrels-a-day)  

                               Aug, 08       P      274,000  FCC, 1.5                
                                 to                          million-metric-tons-a-yea
                               Sep, 08                       (30,400 barrels-a-day)  
                                                             shuts for maintenance.  

                               Aug, 08       P      274,000  Diesel desulfurization  
                                 to                          unit. 1.44              
                               Sep, 08                       million-tons-a-year     
                                                             (30,000 barrels-a-day)  

      Indian Mathura           Aug 25, 08    P      160,000  Hydrotreater shuts for  
      Indian Oil Corp Ltd        to                          maintenance.            
                               Sep, 08                                               

      Indian Panipat           Sep 14, 08    P      120,000  Half the capacity will be
      Indian Oil Corp Ltd        to                          closed.                 
                               Oct 05, 08                                            

      MRPL Mangalore           Oct 02, 11    P      193,800  New Units to expand     
      Oil & Natural Gas Corp     to                          capacity to 15 million  
      Ltd                      Oct 31, 11                    metric tons a year.     

                               Oct 18, 08    P      193,800  CDU, hydrocracker shut  
                                 to                          for maintenance.        
                               Nov 10, 08                                            

      Reliance Jamnagar        Dec 25, 08    P      660,000  New units commission to 
      Reliance Industries Ltd    to                          increase capacity by    
                               Dec 25, 08                    580,000 barrels a day to
                                                             1.24 million barrels a  
                                                             day.                    

                                     *** INDONESIA ***

      Pertamina Balongan       Oct 15, 08    P      125,000  Full shutdown for 57 days
      Pertamina PT               to                          from mid-October. Restart
                               Jan 09, 09                    in mid December failed, 
                                                             full restart postponed to
                                                             Jan. 9.                 

      Pertamina Cilacap        Mar, 09       P      348,000  230,000 b/d No. 2 CDU   
      Pertamina PT               to                          shuts for maintenance.  
                               Apr, 09                                               

                               Aug, 08       P      348,000  Runs cut by 34%, or     
                                 to                          118,000 barrels a day,  
                               Aug 27, 08                    for August maintenance. 

      Pertamina Dumai          Dec 15, 08    U      150,000  Runs cut 15% because of 
      Pertamina PT               to                          fire in tank farm.      
                               Dec 17, 08                                            

      Pertamina Plaju          Mar, 09       P      120,200  CDU shutdown to cut     
      Pertamina PT               to                          refinery output by 25,000
                               Mar, 09                       barrels a day.          

                                       *** JAPAN ***

      Cosmo Chiba              Sep 13, 08    P      240,000  CDU No. 1 restarted Nov.
      Cosmo Oil Co Ltd           to                          10                      
                               Nov 09, 08                                            

      Cosmo Sakai              Aug 22, 08    P       80,000  CDU No. 1 shuts         
      Cosmo Oil Co Ltd           to                                                  
                               Sep 30, 08                                            

      Cosmo Yokkaichi          Sep 28, 08    P      175,000  90,000 b/d CDU No. 5    
      Cosmo Oil Co Ltd           to                          shuts. Restart confirmed.
                               Nov 22, 08                                            

      Idemitsu Aichi           Oct, 09       P      160,000  CDU No. 1, capacity     
      Idemitsu Kosan Co Ltd      to                          160,00 b/d, shuts for   
                               Nov, 09                       maintenance.            

                               Oct 23, 08    P      160,000  RFCC, capacity 60,000   
                                 to                          b/d, shuts for          
                               Nov 20, 08                    maintenance.            

                               Jul 03, 08    U      160,000  RFCC shuts for          
                                 to                          maintenance.            
                               Jul 17, 09                                            

      Idemitsu Chiba           Apr, 09       P      220,000  CDU No. 2, capacity     
      Idemitsu Kosan Co Ltd      to                          220,000 b/d, shuts for  
                               May, 09                       maintenance.            

      Idemitsu Hokkaido        Jun, 09       P      140,000  CDU No. 1, capacity     
      Idemitsu Kosan Co Ltd      to                          140,000 b/d, shuts for  
                               Jul, 09                       maintenance.            

      Japan Kashima            Sep 05, 08    P      270,000  60,000 barrels a day    
      Nippon Mining Holdings     to                          condensate splitter     
      Inc                      Oct 15, 08                                            

                               Aug 26, 08    U      270,000  CDU shuts because of    
                                 to                          operating fault.        
                               Aug 31, 08                                            

                               Jul 10, 08    U      270,000  FCC, capacity 35,500 b/d,
                                 to                          shuts for repairs.      
                               Jul 22, 08                    Restart confirmed.      

      Japan Mizushima          Mar, 09       P      205,200  CDU No. 2, capacity     
      Nippon Mining Holdings     to                          95,200 barrels-a-day,   
      Inc                      May, 09                       shuts for maintenance.  

      Japan Sodegaura          May, 09       P      192,000  CDU No. 2, capacity     
      AOC Holdings Inc           to                          140,000 b/d, and all    
                               Jun 20, 09                    secondary units shut for
                                                             maintenance.            

      Nansei Nishihara         May, 09       P      100,000  100,000 b/d No. 1 CDU   
      Petroleo Brasileiro SA,    to                                                  
      Sumitomo Corp            May, 09                                               

      Nippon Mizushima         Nov 14, 08    N      250,000  CDU No. 2, capacity     
      Nippon Oil Corp            to                          110,000 barrels a day,  
                               Dec 09, 08                    shuts on Nov. 14 on     
                                                             slowing oil demand.     

                               Sep 08, 08    P      250,000  140,000 barrels-a-day No.
                                 to                          3 CDU shuts             
                               Sep 30, 08                                            

      Nippon Negishi           Oct 01, 08    P      340,000  150,000 b/d CDU         
      Nippon Oil Corp            to                                                  
                               Oct 18, 08                                            

      Nippon Osaka             Mar, 09       P      115,000  CDU No. 1, capacity     
      Nippon Oil Corp            to                          115,000 b/d, shuts for  
                               Apr, 09                       repairs.                

      Showa Yamaguchi          Sep 01, 08    P      120,000  120,000 barrels a day CDU
      Showa Shell Sekiyu KK      to                          No. 2 shuts             
                               Oct 06, 08                                            

      Showa Yokkaichi          May, 09       P      210,000  CDU No. 3, capacity     
      Showa Shell Sekiyu KK      to                          135,000 b/d, shuts for  
                               Jul, 09                       repairs.                

      Taiyo Shikoku            Sep 01, 08    N      120,000  Full shutdown after power
      Taiyo Oil Co               to                          cut.                    
                               Sep 02, 08                                            

      Teikoku Kubiki           Nov, 09       P        4,724  4,724 b/d CDU shut      
      Teikoku Oil Co Ltd         to                                                  
                               Nov, 09                                               

                               May, 09       P        4,724  4,724 b/d CDU shut.     
                                 to                                                  
                               Jun, 09                                               

      Toa Keihin               Apr, 09       P      185,000  65,000 b/d No. 3 CDU    
      Toa Oil Co Ltd             to                                                  
                               May, 09                                               

      TonenGeneral Kawasaki    Sep 07, 08    U      335,000  Runs cut because of power
      TonenGeneral Sekiyu KK     to                          failure.                
                               Sep, 08                                               

      TonenGeneral Sakai       Jul 01, 08    N      156,000  CDU shuts after fire.   
      TonenGeneral Sekiyu KK     to                          Restart confirmed.      
                               Jul 04, 09                                            

      TonenGeneral Wakayama    Oct 02, 08    P      170,000  CDU No. 3               
      TonenGeneral Sekiyu KK     to                                                  
                               Oct 30, 08                                            

                               Sep 22, 08    P      170,000  CDU No. 2               
                                 to                                                  
                               Sep 27, 08                                            

                               Jul 08, 08    N      170,000  Shutdown after power cut.
                                 to                                                  
                               Jul 09, 08                                            

                                    *** NEW ZEALAND ***

      New Zealand Whangarei    Sep, 09       P      109,000  New units to expand crude
      BP Oil New Zealand Ltd,    to                          distillation capacity by
      Mobil Oil New Zealand    Sep, 09                       35,000 b/d, to 95,000   
      Ltd, Shell New Zealand                                 b/d, scheduled to start 
      Holdings Co Ltd,                                       in September 2009.      
      Emerald Capital                                                                
      Holdings Inc, Caltex                                                           
      New Zealand Ltd                                                                

                               Feb, 09       P      109,000  Platformer catalyst     
                                 to                          change planned for      
                               Feb, 09                       February 2009. Delayed  
                                                             from November 2008.     

                                      *** PAKISTAN ***

      National Karachi         Nov 04, 08    U       62,500  Full shutdown for       
      Attock Oil Group of Cos    to                          unscheduled repairs.    
                               Nov 14, 08                                            

                                    *** PHILIPPINES ***

      Petron Bataan            Dec 01, 08    P      180,000  Full shutdown for one   
      Petron Corp                to                          month starting in       
                               Jan 01, 09                    December to tie in new  
                                                             Benzene, Toulene, Xylene
                                                             unit.                   

                                    *** SOUTH KOREA ***

      GS-Caltex Yosu           Qtr 1, 10     P      650,000  New Hydrocracker No. 3 to
      LG Group, Chevron Corp     to                          come on line in 2010.   
                               Qtr 4, 10                                             

                               Oct 13, 08    U      650,000  130,000 b/d CDU No. 2   
                                 to                          shuts because of flash  
                               Oct 14, 08                    fire.                   

      Inchon Inchon            Jun, 11       P      275,000  New Hydrocracker 40,000 
      SK Energy Co Ltd           to                          barrels/day construction
                               Jun, 11                       to start June 2008 and  
                                                             operations scheduled to 
                                                             start June 2011
              

      SK Ulsan                 Oct 06, 08    P      840,000  Hydrocracker            
      SK Energy Co Ltd           to                                                  
                               Oct 17, 08                                            

                               Sep 22, 08    P      840,000  Middle Distillation Unit
                                 to                          No. 3 shuts.            
                               Oct 08, 08                                            

                                       *** TAIWAN ***

      CPC Kaohsiung            Oct 15, 08    P      220,000  CDU No. 8, 100,000 b/d  
      CPC Corp Taiwan            to                          capacity, shut for      
                               Dec 09, 08                    maintenance for more than
                                                             40 days, restarted in   
                                                             early December. Residue 
                                                             desulfurization also  
        
                                                             restarted.              

      Formosa Mailiao          Mar, 09       P      540,000  Residue desulfurization 
      Formosa Petrochemical      to                          unit, capacity 80,000   
      Corp                     Apr, 09                       b/d, will be shut for 40
                                                             days.                   

                               Nov 20, 08    P      540,000  CDU, capacity 180,000,  
                                 to                          vacuum distillation unit,
                               Dec, 08                       delayed coker shut until
                                                             the end of December.    

                               Sep 01, 08    P      540,000  80,000 b/d residue      
                                 to                          desulfurization unit.   
                               Oct 18, 08                                            

                               Jul 15, 08    U      540,000  RFCC, capacity 84,00    
                                 to                          barrels a day, shuts for
                               Jul 31, 08                    leaking boiler.         

                               Jul 01, 08    U      540,000  RFCC shuts July 1 for   
                                 to                          10-15 days because of   
                               Jul 13, 08                    boiler leak.            

                                      *** THAILAND ***

      Bangchak Bangkok         Dec, 08       P      120,000  One week shutdown in    
      PTT PCL, Krung Thai        to                          December for maintenance.
      Bank PCL                 Dec, 08                                               

                               Aug 22, 08    U      120,000  CDU shuts after leak.   
                                 to                                                  
                               Sep, 08                                               

      Rayong Sri Racha         Aug 18, 08    P      145,000  Full shutdown for repairs
      Alliance Refining Co       to                          and inspection.         
                               Aug 31, 08                                            

                                      *** VIET NAM ***

      Dung Quat                Feb, 09       P      145,000  New refinery to begin   
      PetroVietnam               to                          production in February  
                               Feb, 09                       2009.                   

      –Editor: Clyde Russell.

Viewing 0 reply threads
  • You must be logged in to reply to this topic.
2923 Topics 3878 Replies

Coking forum

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Curabitur aliquam venenatis venenatis. Vestibulum tempus malesuada rhoncus.

Open forum