      Refinery Status: Exxon Calif. Plant Normal After Brief Flaring
       
      DOW JONES NEWSWIRES July 2, 2010The following table lists unplanned and planned production outages at U.S. refineries as reported by Dow Jones Newswires. The information is compiled from both official and unofficial refining sources and doesn’t purport to be a comprehensive list.
      An unplanned flaring event at ExxonMobil’s (XOM) Torrance, California, refinery had no impact on operations. The event was caused by the unplanned slowdown at an unspecified process unit earlier in the day, a company representative said.
      BP Products North America (BP) Tuesday said operations at its Texas City, Texas, refinery were normal following a brief compressor upset at an unspecified process unit, a filing to Texas state regulators said.
      ConocoPhillips (COP) Monday reported an upset at Unit 40, an FCCU, at its Borger, Texas, refinery. Maintenance has been underway at several units since June 5 and is expected to conclude around July 22, the company said previously. The status of the FCCU is unclear.
      Also at ConocoPhillips on Monday, the company said maintenance continues at its Borger, Texas, refinery following an upset Sunday at Unit 43, a SRU solvent still, that occurred during the restart of units, a filing to Texas regulators said.
      Valero Energy Corp. (VLO) said Monday a coker unit at its Corpus Christi, Texas, refinery was back at planned rates following de-coking maintenance that began on June 20.
      Marathon Oil Corp. (MRO) Friday reported a brief period of flaring at its Texas City refinery during efforts to isolate a small leak in the Alkylation Unit feed bypass line. The event had no impact on operations, the company said.
      For more detailed information, search Dow Jones Newswires using the code N/ REF. Operator Refinery Capacity Description Restart
      (in 000s
      bbl/day)
      UNPLANNED
      GULF COAST

      BP Texas City 455.8 Operations returned to nor- n/a
      Texas mal June 29 following a
      brief upset at an unspecified
      process unit. (TCEQ)

      Lyondell Houston 268.0 CDU hit by fire on May 17 is Jun 20
      TX expected to restart in four
      weeks. 2nd crude unit re-
      started from unplanned mainte-
      nance on May 19. All other pro-
      cess units have been operating
      with feedstocks on hand.

      Marathon Texas City 76.0 Brief period of flaring re- n/a
      TX ported June 25 during efforts
      to isolate small leak at Alky
      lation Unit feed bypass line.
      No impact on production, the
      company said.
      Motiva Port Arthur 285.0 Delayed coker unit jet pump Jun 30
      TX shut for 5-days of repair June
      25; unit will continue to operate.
      Work to conclude June 30.

      Valero Sunray, TX 170.0 FCCU upset when expander coup- mid-Jul
      ling on power train failed June
      16. The unit could be down until
      mid-July, the co. said on June 17.

      MIDWEST

      BP Toledo, OH 125.5 FCCU expected to resume operations
      June 17 after going offline June 15
      due to a boiler failure, a person
      familiar with operations.

      ROCKIES

      Sinclair Casper, 20.0 Refinery running at reduced rates
      Wyo. after explosion, co said. May 27

      WEST COAST

      Chevron El Segundo 279.0 Isomax plant shut March 19 n/a
      CA due to “small” fire. No
      estimate on restart.

      Conoco Ferndale, 100.0 An alkylation unit and butamer n/a
      WA shut following a pump fire early
      June 15, an environmental agency
      said. The refinery continues to
      operate, Co. said June 15.

      Exxon Torrance, 149.0 Flaring event caused by un- n/a
      CA planned slowdown at an unspec
      ified process unit had no im-
      pact on production, co. said.

      Shell Anacortes 145.0 Catalytic Reformer Unit seen at Jun 28
      WA normal rates by June 30; unit
      shut following brief fire on
      June 19.

      Tesoro Wilmington 100.0 Hydrocracker Unit will restart Jun 25
      CA June 25 after shutting down un-
      planned on June 24, a source
      said. The company reported an un-
      planned equipment failure on
      6/24 to state regulators.

      Tesoro Anacortes 120.0 Fire at naphtha unit April 2 end Q2
      WA killed seven. Plant will be shut
      until Sept at least, the co. said
      June 11.

      Valero Benicia, CA 177.0 Coker Unit shut June 19-20 for Jul 29-30
      40 days of unplanned mainte-
      nance.

      PLANNED
      CANADA

      Shell Montreal 130.0 The refinery could be converted
      Quebec into a fuel terminal but Co. said
      its in talks with 2 potential buyers.
      CARIBBEAN

      Valero Aruba 235.0 Idled refinery to restart
      in 90 days after completing
      turnaround, Co. said June 7.
      Valero continues to evaluate
      options for the plant. Tax dispute
      resolved.
      EAST COAST

      Sunoco Westville 145.0 Idling all Eagle Point refin- n/a
      NJ ing operations indefinitely due
      to poor economics, Co. said
      Oct. 6.

      Valero Delaware 210.0 PBF Investments has closed Apr 2012
      deal to buy plant. Petroplus
      said May 5 the plant would be
      restarted in 2Q of 2011.

      Valero Paulsboro 185.0 Small crude unit restarted Jun 19-20
      NJ June 19-20; unit shut June 6
      to facilitate maintenance at
      reformer and hydrotreater.

      Western Yorktown 64.5 Planned work scheduled 3Q 2010. Q3 2010
      VA

      GULF COAST

      Conoco Borger, TX 146.0 Upset at Unit 40, FCCU re- Jul 22
      ported to TCEQ on Jun 28.
      Maintenance continues the Co.
      said June 28. An upset on
      June 27 at an SRU solvent
      still occurred during startup
      of units, a TCEQ filing said.

      Maintenance activity has been
      underway at several units June 5-
      since Jun 5, with emissions from
      units including FCC, GOHDS,
      SCOT unit incinerator, SRU
      incinerator and units 41, 42,
      45 and 98 expected to last unit
      July 22..

      Chevron Pascagoula 330.0 Pre-commercial heavy oil 2010
      Miss. conversion project delayed
      from 2008 to 2010 due to
      economic factors.

      Work is progressing on the
      continuous catalytic reformer,
      expected to be completed by
      mid-2010, Co. said Feb. 25.
      Co. is planning to put a premium
      base-oil facility at plant.

      Flint Corpus $250 mln project for new Spring 2010
      Hills Christi, TX diesel desulfurization,
      sulfur recovery unit to begin
      in Fall 2008. Construction
      to last 18 months.

      Motiva Port Arthur 285.0 Repairs on DCU pump June 8-13.
      TX
      Expansion project to increase 1Q
      throughput capacity by 325,000 2012
      b/d, to 610,000-b/d, slowed.
      Completion now seen 1Q
      2012, from 2010.

      Valero Corpus 340.0 West Plant 50,000-b/d FCCU at
      Christi, TX reduced rates since mid-Dec for
      economic reasons.

      Coker Unit at planned rates Jun 25
      after weekend restart. The
      unit in Complex 7 of the East
      Plant was shut for de-coking
      on June 20.

      Valero Norco, LA 250.0 Upgrade project to build 2012
      a new diesel hydrotreater
      unit moved from 2010 to
      4Q 2012.

      Valero Port Arthur 325.0 77,000-b/d FCCU at reduced n/a
      TX rates since mid-Dec for
      economic reasons.

      Valero Sunray, TX 170.0 55,000-b/d FCCU at reduced n/a
      rates since mid-Dec for
      economic reasons.

      Expanded crude gather system 4Q
      will increase available crude 2010
      supplies to refinery by 4Q.

      MIDWEST

      BP Toledo, OH 155.0 $400 million upgrade 2012
      to start 2010.

      Valero Memphis, TN 195.0 Fire erupted at a selective
      hydrogenation unit April 29;
      it was quickly extinguished.
      One worker in serious condi-
      tion due to burns. Fire damage
      was relatively minor and any
      delay to related FCCU would be minimal, Co. said April 30. Entire plant is in turnaround.
      Work began early March.

      CVR Coffeyville 115.0 New ultra low sulfur gasoline
      unit will be brought online
      in 2Q, Co. said May 3.
      Previous target was to have
      unit up by end of 2010.

      ROCKY MOUNTAIN

      Suncor Commerce 93.0 Planned work at reformer unit Fall
      City, CO deferred to Fall 2010 from Feb 2010
      28 start date.

      Tesoro Mandan, N.D. 60.0 Refinery will return to ser- May
      vice early in May 23 week 21-22
      from turnaround maitenance
      that began on April 19.

      WEST COAST

      Exxon Torrance, CA 150.0 Maintenance at hydrotreater and
      sulfur recovery units restarted, co
      said May 26.

      BP Carson, CA 265.0 Planned flaring activity on
      March 29-April 20 and, Co. reported
      in filings.

      Planned flaring activity reported
      for April 23-May 7, an April 22
      filing said.

      Six days of flaring to begin on
      May 4, a filing stated.

      Conoco Wilmington 139.0 Scheduled maintenance activity
      CA has begun, Co. said April 23. Co.
      declined to provide details about
      the units involved or the schedule.
      Traders familiar with operations
      said work includes a
      hydrotreater.

      Tesoro Golden Eagle 166.0 Turnaround work began in early n/a
      Martinez, Dec at FCCU and alkylation
      CA unit, the Co. said on Feb 3.
      Restart timing unclear.
      Other major turnaround mainte- 2011
      nance deferred to 2011 from
      late 2009, the Co. said Feb 3.

      Tesoro Oahu, HI 94.0 Planned turnaround work will
      Kapolei begin 3Q, 2010, the Co. said
      on Feb 3.

      Planned work deferred to 2011 from
      late 2009, the Co. said Feb 3.

      Chevron El Segundo 279 Flaring took place on May 4, a May 5
      filing said. Traders said it was
      related to a 75k b/d FCCU that went
      down May 4 and was restarted; it is
      operating at 50% of capacity.

      Frontier Cheyenne 47.0 Fall 2010 FCCU, hydrotreater
      WY turnarounds delayed by a year, Co.
      said May 6. FCC delay will limit
      heavy crude processing ability to
      2/3 of capacity.

      (END) Dow Jones Newswires
      06-30-100947ET

Viewing 0 reply threads
  • You must be logged in to reply to this topic.
2923 Topics 3878 Replies

Coking forum

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Curabitur aliquam venenatis venenatis. Vestibulum tempus malesuada rhoncus.

Open forum