Table Of Asia Refinery Maintenance/Shutdown Schedules
May 14, 2010
SINGAPORE -(Dow Jones)- The following table lists maintenance schedules and outages for oil refineries in Asia.
More information will be added as it becomes available. Asia Refinery Maintenance Schedule For Late-2008/2009
Country Company Location Unit(B/D) Period/Duration
Australia Shell Clyde Whole Refinery Nov 2008-TBA
(86,000)
Australia Caltex Australia
Lytton Reformer Sep (30 days)
(N/A)
Australia Caltex Australia
Lytton No. 1 DHT Sep (30 days)
(N/A)
Australia Caltex Australia
Kurnell RFCC March-Early/Late April
(N/A)
India Essar Oil Vadinar Whole Refinery April 16; 15-17 days
(210,000)
India CPCL Chennai No. 3 CDU September; 60 days
(60,000)
India BPCL Mumbai CDU/VDU March 7; 30 days
(120,000)
India BPCL Kochi CDU March 30; 45 days
(60,000)
India MRPL Mangalore Hydrocracker May; 25-30 days
(24,000)
India IOC Panipat CDU September;22 days
(120,000)
CDU
(120,000) March 2010;40-50 days
Indonesia Pertamina Cilacap CDU March (whole month; delayed indefinitely) (230,000)
Indonesia Pertamina Balikpapan CDU Oct (20-25 days)
(60,000)
Japan Idemitsu Tokuyama CDU March 4-10
(120,000)
Japan Nippon Oil Osaka CDU March 8-Apr 1
(115,000)
Japan Japan Energy Mizushima No.2 CDU March 12-May 9
(95,200)
Japan Idemitsu Chiba CDU April-May
(220,000)
Japan Showa Shell Mizue CDU Early April-Early May
(65,000)
Japan Cosmo Oil Chiba No.2 CDU April 25-Jun 20
(130,000)
Japan Fuji Oil Sodegaura CDU May 6-Jun 20
(140,000)
Japan Nansei Sekiyu Nishihara CDU Mid-May, 1-2 Weeks
(100,000)
Japan Showa Shell Yokkaichi No. 3 CDU Late May-Late Jul
(135,000)
Japan Cosmo Oil Sakaide No. 1 CDU Jun 10-Aug 4
(140,000)
Japan Idemitsu Hokkaido CDU Jun-July
(140,000)
Japan Cosmo Oil Sakai No. 1 CDU Aug 22-Nov 15
(80,000)
Japan Cosmo Oil Chiba No. 1 CDU Sep 11-Nov 12
(110,000)
Japan Seibu Oil Yamaguchi Desulfurizer Sep
(51,500)
Japan Seibu Oil Yamaguchi Reformer Sep
(19,000)
Japan Cosmo Oil Yokkaichi No.6 CDU Oct 2-Nov 28
(85,000)
Japan Idemitsu Aichi CDU Oct-Nov
(160,000)
Singapore Exxon Mobil Jurong Several March 1, six weeks
units
S Korea GS Caltex Yeosu RFCC Feb 6-March 20
(90,000)
HDS Feb 6-March 20
(30,000)
S Korea GS Caltex Yeosu No. 4 CDU May 7-June 5-10
(300,000)
S Korea GS Caltex Yeosu hydrocracker May 7-June 5-10
(60,000)
S Korea S-Oil Onsan No. 1 CDU April 1-20
(90,000)
S Korea S-Oil Onsan No. 1 RHDS April 1-27
(53,000)
S Korea S-Oil Onsan No. 2 RHDS October, 26 days
(53,000)
S Korea SK Energy Ulsan No. 2 CDU Jun 3-30
(110,000)
S Korea SK Energy Ulsan Hydrocracker April 2-27
(30,000)
S Korea SK Energy Ulsan No. 1 CDU Early April-TBA
(60,000)
Taiwan CPC Dalin No. 5 Reformer March 5-June 8
(30,000)
Taiwan CPC Dalin ROC Mid June-Mid Aug
(25,000)
Taiwan CPC Dalin No. 6 Reformer Mid July, 2 to 3 months
(30,000)
Taiwan CPC Taoyuan No. 1 RDS April 25-June 10
(30,000)
Taiwan CPC Taoyuan No. 2 RDS Late Jan-March 8
(15,000)
Taiwan CPC Taoyuan VDU April 19-May 17
(36,000)
Taiwan CPC Taoyuan VGH April 19-Aug 1
(20,000)
Taiwan CPC Kaohsiung CDU June 4-July 2
(100,000)
Taiwan Formosa Mailiao No. 1 RDS March 1-April 7-9
(80,000)
Taiwan Formosa Mailiao No. 2 RFCC April 11-April 18-21
(84,000)
Taiwan Formosa Mailiao No. 2 RDS Early Sep, 35-40 days
(80,000)
Note:
TBA – To be announced
CDU – Crude distillation unit
DHT – Diesel Hydrotreater
FCC – Fluid catalytic cracker
HDS – Hydrodesulfurizer
RFCC – Residual fluid catalytic cracker
RDS – Residual desulfurizer
RHDS – Residue hydro desulfurizer
ROC – Residue Oil Cracker
VDU – Vacuum distillation unit
VGH – Vacuum gasoil hydrotreater
VRDS – Vacuum residual desulfurizer
(END) Dow Jones Newswires